1945

The traditions of "Bridge No. 6" were laid during the Great Patriotic War, when, as part of the army, the bridge trains quickly restored bridges and crossings under continuous enemy fire.

On August 31 of 1945 of the year, for the construction of destroyed road-bridge structures and the construction of new ones, the Bridge Restoration Department of the Nevsky-Volkhov basin was created on the basis of bridge trains in Leningrad. For the first post-war five-year plan, the Administration built and reconstructed 138 bridges with a total length of more than 9 kilometers.

1954

After separation from the Ministry of Railways of transport builders and the formation of the Ministry of Transport Construction, the Office received a new name - Trust Bridge Moststroy No. 6.

In the same year, specialists of the trust commissioned the first in the Soviet Union four-way railway overpass through Moskovsky Prospekt in Leningrad with spans 52 m long.

1956

The first reinforced concrete river bridge was erected in Arkhangelsk. A bridge crossing over the Kuznechikha River with a length of 360 meters was built during 3 years. Mostostroy No. 6 was one of the first in the country to master work with spans of this length.

In the same year, specialists of the trust commissioned the first in the Soviet Union four-way railway overpass through Moskovsky Prospekt in Leningrad with spans 52 m long.

1960

A crossing was erected by a trust across the Oyat River on the road connecting Leningrad and Murmansk. During the construction of the bridge, for the first time in our country, the technology of box-type prefabricated reinforced concrete spans of a frame-console system with dry joints between blocks was applied. Later this experience formed the basis for the creation of a number of large bridge structures.

From 1960 to 1978, the trust built 13 similar bridges, including the A. Nevsky Bridge in Leningrad, two bridges across the Velikaya River in Pskov, bridges across the Volga, Sukhona, Vetluga, Mstu and Shosh.

1964

The first bridge over the Northern Dvina was built in Arkhangelsk. During the construction of this movable drawbridge combined with a length of more than 1 km, for the first time in Russian practice, building supports were built on reinforced concrete shells with a diameter of 4 and 6m depth to 50 m at a water level of more than 25m. Metal spans were mounted in a full canopy with a console 176m in length and 2500t in weight using a prestressed spreader.

1965

The longest crossing in St. Petersburg, the Alexander Nevsky Bridge, was put into operation.

The construction, built in 1965 year, had a record for its time channel span of 126 meters. The length of the bridge, along with overpasses and ramps, is 906 meters, width - 35 meters. For the first time, the original principle was applied in the construction of the bridge crossing: steel cables of cable-stayed reinforcement were placed in the hollow tunnels of the longitudinal beams, which, with the inevitable deformation of the crossing, could be pulled up or released to the specified stresses.

1967

A complete reconstruction of the Foundry Bridge in Leningrad. Over the 2 year, the metal structures of the structure were completely replaced, the width of the bridge bed was increased by 10 meters, the turning draw span was replaced by the opening 55 meter span and moved to a deeper place. An adjustable span weighing 3225 tons began to lift hydraulically in just two minutes.

1979

In Cherepovets, the Oktyabrsky Bridge across the Sheksna River is open for traffic, which became the first cable-stayed bridge in Russia. The asymmetric, single-pylon six-lane bridge has a length of about 780 m, the height of the structure is 85 m, and the total length of the cable stay is 16 km.

A capsule with a plate was laid in one of the bridge supports - a message to the descendants: “Today, on the 22 of April 1970 of the year, on the day of the 100 anniversary of the birth of V.I. Lenin, the team of V.I. Batishchev of the bridge train No. 809 of the Leningrad trust“ Mostostroy No. 6 ", having scored the first pile, proceeded to the construction of a bridge over the Sheksna River in the city of Cherepovets."

1980-e

By the beginning of the 80's, Mostostroy No. 6 became the largest organization in the country specializing in the construction of road and railway bridges, overpasses, overpasses, tunnels and moorings. In 1981, the company was awarded the highest award of the Soviet era for its activities - the Order of Lenin. In the same year, the Ladoga drawbridge across the Neva was put into operation.

The Ladoga bridge connects the Neva coast in the place where in January 1943 of the year there was a unique tree-ice crossing for T-34 tanks. On the left bank of the bridge’s abode there is the Museum-Diorama “Breakthrough of the Siege of Leningrad” opened in 1983. A monument was installed near the bridge - the T-34 tank. The bridge, diorama and monument are part of the Breakthrough memorial complex.

***

In July of the 1983 of the year, the USSR’s first submarine road and pedestrian Cannoner tunnel, constructed using the lowering section method, began operating.

All work was carried out without stopping the movement of large vessels along the Sea Canal of the Leningrad Trade Port and trains in the vicinity of the nearby railway station.

***

Since 1986 of the year, Mostostroy No. 6 took part in the construction of railway bridges. Obskaya-Bovanenkovo ​​on the Yamal Peninsula to the Bovanenkovo ​​gas condensate field.

Specialists of the trust in the conditions of permafrost built 7 of capital and temporary railway and combined bridges.

***

A pedestrian bridge was built in Novgorod, which has become one of the symbols of the city.

A three-span continuous beam bridge was constructed with curved (arched) outlines of the lower zone. The total weight of the metal structure was 800 tons. According to technical specifications, about 8000 people can simultaneously be on the bridge.

1990-e

1980 completed the construction of one of Europe’s largest automobile bridge crossings - the Krasnoflotsky bridge across the Northern Dvina in Arkhangelsk. The length of the bridge, including the left-bank overpass and bridges across the left and right branches of the Northern Dvina, was 3950m.

***

Reconstruction of the Volodarsky bridge in St. Petersburg. During the work, 800-ton 125-meter spans were installed on the right-bank and left-bank abutments, which were then connected by an 57-meter adjustable span. To ensure communication between the districts of the city, a temporary bus and pedestrian bridge was built during the reconstruction period.

In the same year, experts of the trust erected an overhead extension for the tram congress near the bridge.

***

In 1993, the trust was transformed into the Open Joint-Stock Company Bridge Construction Trust No.6. Since that time, having fully retained its personnel and production potential, the company has been actively involved in the formation of new market relations, expanding the directions and geography of its activities.

A bridge was built across the Sukhona River in the village of Nyuksenitsa, Vologda Oblast. At the time of construction, it was the first bridge in Russia with a maximum span of 105m, pulled without the use of temporary supports, using a universal rigid spreel.

***

The Bolsheokhtinsky bridge was reconstructed in St. Petersburg. At the same time, more than 3000 steel structures were installed, more than 48000 square meters of asphalt and about 10000 cubic meters of concrete were laid.

In 1997, in the All-Russian competition for the best construction organization, Mostostroy No. 6 was awarded a diploma of the 1st degree, and the company took the 4 place in the rating of the best construction and installation organizations in Russia.

***

The reconstructed bridge over the Saimaa Canal in Vyborg was commissioned.

During the work, the supports of the existing structure were left without restructuring, and all the spans were replaced. Reinforced concrete side spans were replaced with metal, the adjustable span was disassembled and replaced with a metal non-adjustable span, similar to the side spans of the bridge.

***

The Pavlovsky bridge over the Saimaa Canal was built on the bypass of Vyborg. A bridge with a length of 434 m with spans of up to 100m and a height of supports of up to 30 m for passage of ships was built in 14 months.

Pavlovsky bridge is included primarily in the construction of the Vyborg bypass. The 6,6 km bypass section took place in difficult geological conditions. Numerous boulders, the diameter of which exceeded three meters, and granite rock, through which the route was conducted, required blasting.

2000-e

The reconstruction of the Krasnoluga bridge in Moscow has been completed. The structure was erected on the supports of a bridge built at the beginning of the 20 century during the construction of the Moscow Ring Railway. Reconstruction works were carried out in a short time, in the conditions of dense urban development, with many communications and heavy traffic. The length of the bridge is 135 meters, weight - 1400 tons.

The bridge of Alexander Nevsky in St. Petersburg was reconstructed.

***

A transport interchange was built at the intersection of the St. Petersburg ring road with the railway and Primorsky highway in the vicinity of Gorskaya station.

This traffic intersection is the most complex artificial structure in this section of the Eastern Ring Road. In the construction zone of the interchange, the reconstruction of engineering networks (water supply, sewage, electrical networks, communication networks, railway communications, etc.) was carried out.

***

Overhaul of the Finland railway bridge across the Neva in St. Petersburg. In 2002-2003 years, in connection with the construction of the Ladoga station, the company made a major overhaul of the bridge. During the repair, an adjustable span and an adjustable mechanism were mounted, the towers were repaired, the carriageway was replaced, as well as the overpass adjacent to the bridge.

***

Mostostroy No. 6 has commissioned 34 road transport facilities, including 13 bridges and overpasses. The total length of the facilities was 2872 m. A bridge was built across the Sheksna River near the village of Ivanov Bor in the Vologda Oblast. The construction of the bridge made it possible to eliminate the ferry crossing, ensuring uninterrupted communication between the central and northwestern regions of Russia and the regions of the Vologda Oblast.

***

In 2006, the company took part in the construction of one of the most complex hydrotechnical construction projects, implemented in accordance with the German-Russian project for the disposal of nuclear submarines. Mostostroy No. 6 acted as general contractor for the construction of a complex designed to reload submarine reactor compartments at a long-term storage facility in the Sayda Bay (Murmansk Region).

At the same time, Mostostroy No. 6 commissioned a bridge with a unique arch span 160 m long across the Bolshaya Okhta River on the St. Petersburg ring road. A similar construction was built in Russia for the first time: arches with all-welded mounting joints have a slope towards the drive axis and are connected to the stiffener with cables. Installation of the arch span was carried out by the method of longitudinal and transverse movement using a floating support.

***

In the 2007 year, Mostostroy No. 6 conducted work at 67 facilities, of which 49 were commissioned. Among them are the pedestrian bridge at the Obukhovo station of the Oktyabrskaya Railway in St. Petersburg, the bridge over the Utka River of the first stage of the construction of the ring road around St. Petersburg on the site to the Rossiya highway, the overpass over the railways on Leningradskaya Street in Vologda. In addition, the company carried out major repairs of the road leading from St. Petersburg to the border with Norway and passing through Petrozavodsk, Murmansk and Pechenga.

***

Of the 60 facilities that were under construction in the 2008 year, Mostostroy No. 6 commissioned 47 facilities. In particular, the construction of the main exit section and 5 congresses of the Western High-Speed ​​Diameter were completed.

The reconstruction of the Neva overpass in the alignment of Narodnaya Street and the Murmansk Highway through the Oktyabrskaya Railway line in St. Petersburg was completed.

The reconstruction project involved the expansion of the overpass to 6 strips of 3,75 m wide. During the work, a two-lane doubler was added to the existing structure, the old spans were preserved. As a result, the overpass and approaches to it have been expanded from four lanes to six.

All work was carried out without blocking the movement.

***

Mostostroy No. 6 carried out work at the 51 facility, 27 of which are bridges and overpasses.

In 2009, in St. Petersburg, a single-span non-movable cable-stayed cable-stayed Lazarevsky bridge with four-lane traffic was built on the site of an old wooden crossing. The modernization of the structure significantly reduced the transport load on the Bolshoi Krestovsky bridge, on which, until that moment, all traffic to Krestovsky island was carried out.

Traffic on the bridge is open ahead of the contract deadlines for 3 months.

2010-e

In July 2010 of the year, Mostostroy No. 6 completed the reconstruction of a complex of railway bridges across the Obvodny Canal in the Moscow direction of the Oktyabrskaya Railway (American bridges). Work on bridges built in the second half of the 19th century took place as part of a comprehensive reconstruction of the Obvodny Canal embankment. The project provided for the reconstruction of 5 bridges and the reconstruction of the adjacent railway infrastructure.

In 2010, Mostostroy No. 6 completed the work and commissioned the Yagorbsky (Cherepovets) and Bolshoi Petrovsky (St. Petersburg) bridges, a bridge over the river. Shuya and 3 transport interchanges on the highway St. Petersburg - Pechenga.

***

In 2011, Mostostroy No. 6 conducted work on 27 facilities.

In the autumn of 2011, the 2 facility commissioned for St. Petersburg University of the State Fire Service of the Ministry of Emergencies of Russia was commissioned: the 6-storey building with a total building area of ​​4775 m2 for the university in St. Petersburg, and the 2-storey building of a household building with a total building area of ​​1 932 m2, intended for cadets and officers of the Siberian Institute of Fire Safety (a branch of the university in the Krasnoyarsk Territory).

***

In July 2012, traffic was opened on a new bridge over the Shirokaya Broad Salma River at 1197 km of the Kola highway. Next to the old bridge, a new structure was built with a length of 100,03 m, a roadway width of 10 m with 2 lanes for vehicles. The old bridge is dismantled.

***

In 2013, Mostostroy No. 6 carried out work on 40 facilities, about 20 of which were transport infrastructure facilities. Including unique projects - the construction of an offshore basin for the Krylov Research Institute for conducting complex hydrodynamic tests of marine equipment, tower evaporative cooling towers with a height of more than 170 m (172,5м) for power units of RoNPP and NNPP-2, construction of infrastructure for handling SNF and RW.

At the beginning of 2013, Mostostroy No. 6 began construction of three large transport infrastructure facilities in St. Petersburg: the interchanges at the intersection of Piskarevsky Prospect and Nepokoreny Avenue, driving along the southern shore of the Obvodny Canal from the Glukhoozerskoye Highway to Obukhovskaya Defense Avenue, with an interchange with Obukhovskaya Defense Avenue, interchanges at the intersection of Zelenogorsk highway and Bolshoi Prospekt Kurortny district of St. Petersburg with the railway ways of the Vyborg direction in the area of ​​railway Repino station.

In July 2013, traffic was opened on the reconstructed bridge over the Syasya River at 515 km of the A-114 Vologda - Novaya Ladoga highway in the Leningrad Region. The length of the bridge is 182,3m, the total width of the bridge is increased from 8,72m to 14,4m. Work on the modernization of the crossing has been carried out since July 2011, without stopping the movement of water and vehicles.

In July, the construction of the exhaust part of the tower evaporative cooling tower for power unit No. 3 of Rostov NPP-2 was also completed, and the first tier of the evaporative cooling tower for power unit No. 4 began concreting. After completion of work on the exhaust shell at the facility, the installation of internal supporting structures, installation of technological equipment was carried out.

In September, reconstruction of the Obvodny Canal embankments from Dnepropetrovskaya Street to Ataman Bridge in St. Petersburg was completely completed. The work was carried out in two stages: at the first stage, the reconstruction of the railway complex was completed bridges over the canal. On the second, the embankments were reconstructed with lowering the level and widening the carriageway to 4-6 lanes.

07.08.2015

The company "Mostostroy No. 6" congratulates all employees on the day of the builder!

22.06.2015

Crocus International has entered into a strategic agreement with Bridge No. 6 for the construction of the Central Ring Road

03.06.2015

The Minister of Transport of the Russian Federation Maxim Sokolov has opened traffic on the bridge across the river. Volkhov on the P-21 Cola highway